A38 Gloucester Road, Almondsbury – Bridge refurbishment works

The bridge deck at this location is in need of refurbishment to ensure the durability of the structure.  Works are extensive and will include repair of concrete, drainage, and the footway. In addition, we will replace waterproofing and bridge joints and finally renew the surfacing. We’ll work mainly during daytime hours and the bridge will remain open throughout most of the works.  

Traffic management

Phase 1: 13 November to 3 January 2022

  • 2 narrow lanes and a 30mph speed limit will be in place on the bridge deck
  • A 24/7 bridge closure is planned from 6 am 14 November to 6 am 15 November

Phase 2 and 3: 4 January to June 2022

  • Two-way temporary traffic lights and a single lane will be in place on the bridge deck
  • Planned overnight closures – 8 pm to 6 am the following morning
    • 4 January 2022
    • 28 January 2022
    • 6 March 2022
    • 30 & 31 March 2022
    • 1 & 2 June 2022

Locally signed diversions will be in place for light traffic. HGV’s will be diverted via M5 J14 to J16 and vice versa. Please note these closures may be subject to change.